Our experience and ability to accommodate to our clients' requirements lets us undertake the execution of untypical tasks which are technologically complicated.
In 2000, ew carried out an untypical, first time in Poland technologically dificcult task of laying approx. 9 km of medium-voltage cable 15kV of special construction on the bed of Czorsztyn Lake.
MANSTEL company managed to transport the 32-ton drums with cable on water. Drums were placed on a platform especially constructed for this purporse of elements of a military pontoon bridge.